Status of Supply, installation & commissioning of 207 Water Injection metering systems:

ROSHAN KUMAR SINGH
2024-04-13 09:19:22
Status of Supply, installation & commissioning of 207 Water Injection metering systems:Project progress = 56%.All the 207 WI meters including isolation valves, spools, PTs, Cables/Cable trays and Servers delivered at the platforms. Work execution started at MHN, BHS, SHP & ICP. Total 9 meters (MHN-5, BHS-2, ICP-2) are installed as on 12.04.2024. EDC: Jan 2025114 water injection metering project:The cost estimation for remaining 114 WI strings works out to be approx. 12 Cr as per the LPP of 207 case and as per the new guidelines, this case is to be handled by CPD. DISHA file handed over to NTA for further processing of the case by NTA/CPD.